Sudden Surge in Budhi Gandaki River Causes Losses to 412 MW of Power Capacity
A flash flood on the Budhi Gandaki River in Gorkha’s Chumanubari Rural Municipality on Sunday morning caused widespread damage to four privately owned hydro projects. According to IPPA‑N, the combined installed capacity of the affected projects is 412.09 megawatts. The 341 MW Budhi Gandaki project’s central camp was submerged, washing away several pieces of heavy equipment. In the 24.5 MW Dobhan Khola scheme, some workers’ houses were damaged and a Bailey bridge over the river collapsed. The 30.59 MW Yaru Khola site also lost its temporary bridge and construction supplies, while the 16 MW Machha Khola project suffered a destroyed access road and river bridge. The event follows the destructive August floods that battered the Bhote Koshi and Trishuli basins, underscoring the climate‑related risks facing Nepal’s ambition to become a major hydropower exporter.