WASHINGTON — In an effort to avert a possible electricity shortfall, the Department of Energy issued an emergency directive on August 20 permitting a Maryland generating station to exceed its licensed output.

The order, invoked under Section 202(c) of the Federal Power Act, targets Unit 4 of the Wagner Generating Station in Anne Arundel County. By allowing the unit to operate above its usual ceiling, the government hopes to satisfy rising demand across the Mid‑Atlantic’s 13‑state footprint and the District of Columbia.

Energy Secretary Chris Wright explained that the move protects roughly 65 million customers from disruptions. The directive is scheduled to remain active until November 17, giving grid operators a window to stabilize supply.

PJM Interconnection, the regional reliability entity, coordinated with Talon Energy Corporation to implement the higher‑output schedule. PJM had previously requested federal involvement, citing concerns that the unit would be essential during peak consumption periods.

The decision comes amid growing pressure on the U.S. power network from climate‑driven temperature extremes, the retirement of aging plants, and expanding electricity needs of data centers, AI platforms and heavy‑industry facilities.

Mid‑Atlantic states, particularly Northern Virginia, are home to a dense concentration of data‑center infrastructure that powers cloud services worldwide. The surge in AI‑driven workloads is prompting tech giants to pour billions into new facilities that demand uninterrupted power and robust cooling.

Officials underscored that the temporary measure is designed to enhance grid reliability, ensuring that households and businesses continue to receive safe and affordable electricity while longer‑term solutions are pursued.