In a Friday ruling, the nation’s highest court granted a temporary stay that permits the Trump‑backed ballroom construction at the White House to proceed. The stay, authored by Chief Justice John Roberts, suspends the lower courts’ orders that would have stopped the work.

According to documents submitted by the administration, the $400 million privately financed venture was already more than halfway complete by mid‑August. Roughly 250 construction workers are said to be on site, operating up to twenty hours per day throughout the week.

The Supreme Court’s move follows a July 7 decision by the District of Columbia Circuit Court of Appeals, which had deemed the project illegal and put a two‑week hold on construction to allow an appeal.

Preservation groups, including the National Trust for Historic Preservation, contend that the project proceeded without mandatory environmental review or congressional consent, effectively stripping historic parts of the East Wing to make room for a massive ballroom.

Support for the expansion has come from several White House officials and some members of Congress, yet a number of Republican legislators have expressed reservations about the lack of oversight.

President Trump has repeatedly described the renovation as a demonstration of American strength and a visual statement of the country’s revival, comparing the planned space to grand halls abroad.

The stay does not address the underlying legal questions, meaning the final decision on the project's legality remains pending.