Hyderabad, September 24 – After the Yadadri thermal power station halted output due to a lack of G‑9 grade coal, the Telangana cabinet issued a directive to secure the fuel from external suppliers. Under the leadership of Chief Minister A. Revant Reddy, the Energy Department will initiate procurement from Great Indian Coalfields and Coal India Ltd.

Deputy Chief Minister Mallu Bhatty Vikramarka announced that he will meet with Union Coal Minister Kishan Reddy to confirm the quantity and timeline for the G‑9 coal supply needed to restart the plant. The meeting is expected to take place within the next few days.

A senior review panel highlighted that the plant’s location, chosen by the previous government, is distant from major coalfields, imposing an extra logistical cost of roughly 40,000 crore rupees on the state. The panel also noted that Singareni mines lack the necessary G‑9 coal blocks, and past decisions not to bid in coal auctions have left the plant without adequate fuel.

To avoid prolonged power outages, officials have been instructed to source coal on a temporary basis from the two central agencies while the state evaluates longer‑term options, including potential new mining blocks or alternate fuel mixes.