New PPP Policy 2026 Aims to Accelerate Maharashtra Infrastructure
Mumbai, October 27: In a move aimed at boosting infrastructure development, the Maharashtra cabinet on Tuesday approved key structural and procedural changes to the state's Public-Private Partnership Policy 2026. The meeting was chaired by Chief Minister Devendra Fadnavis.
Officials see the decision as a significant step toward streamlining how infrastructure projects are planned, approved, and executed across Maharashtra.
The revised framework comes after cabinet approval and seeks to add clarity to infrastructure projects statewide. It also aims to simplify administrative processes and raise efficiency. The policy draws its guiding direction from point 100 of the 'Viksit Maharashtra 2047' vision document.
Funding and Clarity
The state has allocated Rs 200 crore under Viability Gap Funding (VGF) for the financial year 2026-27. The changes were introduced after the Maharashtra Institution for Transformation (MITRA) called for greater clarity and simplification. In all, the policy now includes 11 major amendments.
The revised policy provides a clear definition of Viability Gap Funding. It also lays down updated guidelines on ownership and risks between developers and project authorities for situations where the policy does not apply.
Faster Approvals
To cut down on administrative delays, one stage of review by the Network Planning Group committee has been removed from the process of in-principle approval for projects.
MITRA's Chief Executive Officer will now be invited to Cabinet Infrastructure Committee meetings during the approval stages of PPP projects. Projects that involve government assistance, land, or a premium of up to Rs 25 crore must obtain formal approval from the Empowered Committee.
Projects worth Rs 25 crore or more will need clearance from the Cabinet Infrastructure Committee (CCI), based on the Empowered Committee's recommendations.
Strengthened Governance
The policy has also been improved in several areas, including Project Development Fund (PDF) support, departmental project evaluation, development through Special Purpose Vehicles (SPVs), project sanction, and the appointment of Transaction Advisors and law firms.
A notable addition is a new policy concept under Clause 13, which covers asset monetisation. The aim is to earn revenue by increasing the economic value of public assets such as land and buildings. Such assets may not be commercially viable under the regular PPP model, yet they can be utilised in ways that support the goals of the Viksit Maharashtra 2047 vision.
Step-by-Step Process
According to the updated guidelines, PPP projects will follow an organised process from start to finish. The concerned department will carry out an initial feasibility study, a public interest assessment, and a value-for-money analysis. Departments will also have the option of drawing support from the Project Development Fund.
A techno-economic feasibility report, draft Requests for Proposals (RFPs), and concession agreements will be prepared with the help of transaction advisors and law firms.
Before a project is taken to the market, essential preliminary clearances, including EC and CCI approvals, will be secured. A transparent competitive bidding process, evaluated on a single financial criterion, will follow.
The Empowered Committee will handle final approval, sign concession agreements with the selected developers or SPVs, and oversee implementation closely. A grievance redressal mechanism will also be established for matters involving more than Rs 5 crore.