Madhya Pradesh PWD suspends contractor registration after spot‑check reveals flaws
Random inspections carried out by the Madhya Pradesh Public Works Department have triggered decisive action against both officials and a private contractor. Four departmental officers were served with formal notices demanding explanations for the irregularities discovered during the audit of 34 ongoing and completed works.
The audit covered projects under the state PWD (road and bridge), the Project Implementation Unit, the Madhya Pradesh Road Development Corporation, and the Madhya Pradesh Building Development Corporation. Teams from seven districts – Raisen, Pandhurna, Shivpuri, Burhanpur, Umaria, Mandsaur and Niwadi – inspected the sites and reported back to Chief Engineer R.L. Verma via a video‑conference meeting.
One of the critical findings involved a high‑grade bridge spanning the Pandarol Nala in Burhanpur. Quality deficiencies prompted the chief engineer to instruct the divisional officer and the acting executive engineer to issue showcause notices immediately.
Another problematic case was the Hivra‑Haiderpur road work, where sub‑standard construction prompted notices to the supervising officer and assistant engineer. The department also ordered the suspension of registration for Kalika Furniture Industries, the contractor responsible for the work in Khandwa, until corrective measures are verified.