Raipur: CG-RERA Takes Strict Action Against Unregistered Project

By News Analysis India · · 2 min read

The Chhattisgarh Real Estate Regulatory Authority has taken strict action against a real estate project in Raipur that was both incomplete and unregistered. The move underlines the regulator's focus on safeguarding homebuyers and enforcing the RERA Act.

The case concerns the 'Vatsalya Gaurav-1, Phase-1' project located at Sejbahar in Raipur district. The authority has ordered the promoter to pay Rs 6,87,496 in interest to an allottee, along with a monthly payment of Rs 7,314 until the project receives its completion certificate.

Why the Authority Acted

During the proceedings, the authority found that the project's development work had not been carried out as per the sanctioned layout. The promoter had also failed to obtain a completion certificate from the competent authority.

Based on these findings, the project was classified as incomplete and ongoing. The authority therefore ordered the payment of interest for the delay under Section 18 of the Real Estate (Regulation and Development) Act, 2016.

Details of the Interest Order

The promoter has been asked to pay interest of Rs 6,87,496 on the Rs 8,12,643 paid by the allottee. The calculation uses an annual interest rate of 10.80 percent for the period from 2019 to October 2026.

Beginning 1 November 2026, the promoter must pay Rs 7,314 per month to the allottee until the completion certificate is obtained.

Action Over Lack of Registration

The authority has also taken a serious view of the project's failure to register with RERA. According to the order, eligible projects must be registered under Section 3 of the Act.

Because the project remained unregistered, a separate case has been ordered against the promoter under Section 59 of the Act.

Selling Plots Does Not End Responsibility

The order highlights that a promoter's obligations do not end once plots in a project have been sold. Development work such as roads, drains, electricity and drinking water supply must be completed as per the approved layout.

The promoter must also ensure essential infrastructure and secure the required certificates from the competent authority.