Gujarat's First Bullet Train Traction Substation Enters Final Phase

By News Analysis India · · 1 min read

Ahmedabad, October 30: The first traction substation being built at Bilimora in Gujarat's Navsari district for the Mumbai-Ahmedabad bullet train project is now in its final phase of construction.

This substation is the first of 14 planned along the 508-kilometre high-speed rail corridor. The facility spreads over roughly 18,000 square metres and is advancing steadily.

Equipment installation, testing and commissioning are moving forward quickly. The buildings already house control panels, changeover switches, transformers and circuit breakers. All gantry towers and beams have also been fully constructed.

Across the corridor, a total of 14 traction substations are being developed to keep electricity flowing to trains without interruption. They draw power from the electricity grid, step it up or down to the necessary voltage, and pass it on to the traction power system that drives the trains.

Five of these substations are in Maharashtra, at Mumbai, Thane, Virar, Boisar and the Thane depot. The other nine are in Gujarat, at Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand, Mehemdabad, Ahmedabad and the Sabarmati depot.

The Gujarat substations will receive power from GETCO's 220 kV Ambheta grid substation. From there, a 2x25 kV traction power supply system will deliver electricity to the overhead equipment (OHE) installed on the viaduct.

The overhead lines carry the power to the trains, which receive energy through pantographs on their roofs. A centralised control centre will monitor the whole traction power network in real time, keeping a close watch on supply along the entire route.

India's first bullet train project, the 508-kilometre Mumbai-Ahmedabad high-speed rail corridor, connects Maharashtra and Gujarat. These traction substations form a vital component of its power infrastructure and are essential to the smooth running of bullet trains on the line.