Vikramshila Bridge Schedule: Bailey Bridge Opening and Future Repair Plans

The opening of the Bailey Bridge on June 7 marks a temporary solution for the residents of Bhagalpur. However, a total shutdown of the Vikramshila Setu is scheduled from September 15 to November 30...

By News Analysis India · · Updated · 1 min read

The opening of the Bailey Bridge on June 7 marks a temporary solution for the residents of Bhagalpur. However, a total shutdown of the Vikramshila Setu is scheduled from September 15 to November 30 for extensive permanent repairs. During this closure, three damaged slabs will be replaced with a permanent truss bridge structure. Road Construction Minister Engineer Shailendra stated that the goal is to complete all major repairs by late November, allowing for the full resumption of both light and heavy vehicle traffic by early December.