Patna-Purnia NE-9 Expressway: 245 km and 322 Underpasses

By News Analysis India · · 3 min read

Bihar is preparing for a major infrastructure milestone with the Patna-Purnia Expressway, the state's first national expressway. Designated as NE-9, the 245-kilometre corridor carries an estimated capital outlay of around Rs 31,987 crore, and construction will be formally started by Prime Minister Narendra Modi on November 20.

The four-lane greenfield road is designed for a speed of 120 km per hour and has been planned for future widening to six lanes. Officials expect the trip between Patna and Purnia, which currently takes seven to eight and a half hours by road, to shrink to roughly three hours after completion.

Notably, this is the first time a greenfield national expressway is being built entirely within Bihar's borders.

The Alignment

Work will start at NH-22 near Mirnagar Areji in Vaishali district, close to Hajipur. The road will then travel through Narharpur, Harlochanpur, Bajidpur, Saraunja, Rasna, Porora and Fatehpur before meeting NH-27, the East-West Corridor, at Hansdaha in Purnia district. The entire stretch measures 244.96 km. Because it links to the Patna Ring Road, the expressway will help commuters heading to Patna as well as travelers bound for Purnia and Kishanganj.

The centre notified the Hajipur-Purnia greenfield route as NH-9 through a gazette notification dated July 29, 2025. Preliminary land acquisition notices had already been issued in March 2025.

Cost and Financing

The civil works for the road itself have been estimated at Rs 12,052 crore. Under the Hybrid Annuity Model, the government will contribute 40 per cent of the project cost, while the construction firm will invest 60 per cent. The firm's returns will come from toll revenue.

The project is split into three construction packages. Package one runs 84.500 km from Mirnagar Areji to Bhirha and is priced at Rs 10,083.96 crore. Package two covers 51.835 km from Bhirha to Saraunja at Rs 8,564.82 crore and includes a planned 7.020 km six-lane Kosi bridge between Kusheshwarsthan and Simri Bakhtiyarpur. Package three extends 108.625 km from Saraunja to Hansdaha at an estimated Rs 13,338.32 crore.

Land and Districts

Land acquisition is currently under way across 29 blocks in six districts. More than 250 villages have been marked for the project. Vaishali has six blocks, Samastipur eight, Saharsa five, Purnia six, and Darbhanga and Madhepura two each.

A total of 2,236.003 hectares is required. Of this, 53.091 hectares is forest land, 37.18 hectares is government land and 2,117.218 hectares is private land. The acquisition is proceeding under the National Highways Act, 1956, with compensation to be determined through official norms and valuation.

Structures and Features

The corridor will feature 21 major bridges, 140 minor bridges, 11 railway overbridges, 21 interchanges and 322 underpasses. Water crossings will be built over 20 rivers and channels, among them the Bagmati, Kamla, Kosi, Budhi Gandak, Bayaa, Kareha and Libri Dhar.

Better Access for Districts

Spur roads are planned to connect the headquarters of Samastipur, Saharsa and Madhepura to the main highway, sparing residents long detours. The expressway will also serve 18 cities and towns, including Hajipur, Ujiarpur, Rosera, Kusheshwarsthan, Simri Bakhtiyarpur, Bihariganj and Purnia. It will link with nine national highways, eight state highways and five airports.

A Boost for Seemanchal

Industry watchers say the road could transform farming and trade in the Kosi and Seemanchal belts by making it easier to move produce to big markets. Food processing, logistics and manufacturing are also expected to gain. Today, travelers choose between a route through Muzaffarpur, Darbhanga and Supaul, which takes eight to eight and a half hours, and one through Bakhtiyarpur, Mokama, Khagaria and Katihar, which takes about seven hours. The expressway will cut the trip to three hours.