Mokama New Railway Bridge Triggers Massive Train Rerouting and Cancellations
A new railway bridge parallel to the 1959‑era Rajendra bridge is being erected near Mokama in Bihar. Because the interlocking system must be installed before the structure can be commissioned, the rail network will see a temporary diversion of 384 train services.
The diversion is part of a broader plan that also includes 56 partial shutdowns and the commencement of 67 services on alternative routes. Between 20 September and 4 October 2026, a total of 67 train numbers will be completely cancelled, with a peak of 36 cancellations on 3 October.
The existing Rajendra bridge supports only a single line, and widening it is not feasible due to engineering limitations. Over the past 60 years, passenger and freight traffic have increased dramatically, leading to frequent delays, especially before Baruni station.
The project received approval in the 2015‑16 railway budget with a budget of ₹1,491.47 crore. The foundation stone was laid by the Prime Minister on 12 March 2016. The new bridge, together with its approach tracks, will stretch about 14 km and feature nine auxiliary river bridges, two road‑over‑rail bridges and three rail‑over‑rail bridges, all linked directly to existing stations such as Handi‑dah, Tal, Rampur Dumra, Rajendra Bridge and Baruni.
A detailed schedule of cancelled trains has been issued, featuring numbers like 13029 Howrah‑Mokama Express, 13031 Howrah‑Jaynagar Express, 13127 Kolkata‑Ara Express, 13415 Maldah Town‑Patna Express, among many others. Travelers should monitor official updates for re‑routed itineraries and reservation changes.